SEMSWA Website

Home

About SEMSWA

Stormwater Basics

What We Do

Who We Serve

Who We Are

Our History

Bids Proposals Contracts

Board Meetings & Calendar

Community Outreach

Projects

Before & After Gallery

CIP Projects

Drainage Master Plans

Maintenance Projects

Fees

Credits

Stormwater Fees

SDF & ECF

Review and Permit Fees

Floodplains & Flooding

Am I in The Floodplain?

Flood Safety

Regulations & Permitting

Permits

Floodplain Permit

GESC Permit

Public Improvement

Resources & Downloads

Manuals & Templates

Mapping Resources

Budget & Annual Reports

Programs

CIP

Water Quality

Floodplain

Maintenance

Master Planning

Land Development

GIS

External Links

Job Opportunites

Contact Us

Grading, Erosion, and Sediment Control (GESC) Permit


General Information

SEMSWA issues Grading, Erosion, and Sediment Control (GESC) permits within the City of Centennial and unincorporated Arapahoe County for all disturbances outlined in the GESC Manual.  These permits are typically issued in association with new development, redevelopment, or utility projects.  If you think you need a permit, please call SEMSWA at 303-858-8844 and ask to speak with one of the GESC engineers, or email us at semswamain@semswa.org.  Click here if you'd like to know more about water quality requirements.


Application for Review & Permit Fee Calculation

  • Application for Review and Approval (to be attached and completed for each submittal made to SEMSWA)
  • Permit Fee Calculation (click link to estimate the permit fees for your project)

Standard GESC Permit Instructions

Refer to GESC Manual Section Reference for Additional Information

1.  Apply for GESC permit

  • Pickup approved GESC plans, a copy of the GESC Field Manual, Permitting Instruction Packet (2.13)
  • Complete GESC Permit application and submit to Southeast Metro Stormwater Authority (SEMSWA) with Fees (2.14)
  • NOTE:  A GESC permit is included in this packet and can be obtained from SEMSWA
  • Provide GESC permit fee due with GESC Permit Application
  • Provide Collateral with the GESC Permit Application (2.16)

2.  Prior to GESC Permit Approval

  • Designate a GESC Manager and Alternate GESC Manager
  • NOTE:  A GESC MANAGER MUST BE DESIGNATED PRIOR TO THE PRE-CONSTRUCTION MEETING.  THE GESC MANAGER DESIGNATION FORM SHALL BE SUBMITTED TO SEMSWA AT THE PRE-CONSTRUCTION MEETING.
  • Review GESC Field Manual, GESC Plans, and related plans and permits (5.2.3)
  • Install Initial BMPs in accordance with approved GESC Plans (5.3.1)
  • Schedule GESC Pre-Construction Meeting (5.3.3) with SEMSWA
  • Contact:  Dan Olsen - 303.858.8844

3.  Throughout Duration of GESC Permit

  • Provide regular GESC inspections in accordance with the GESC Manual
  • Ensure proper installation and maintenance of BMPs as required within the GESC Manual (5.7, 5.8)
  • NOTE:  THE GESC MANAGER WILL BE REQUIRED TO CERTIFY ALL REQUIRED GESC INSPECTIONS AT BOTH THE INITIAL CLOSE-OUT ACCEPTANCE AND FINAL CLOSE-OUT ACCEPTANCE.

4.  GESC Permit Close-Out

  • Initial Close-Out can be requested when all improvements are completed, and the site/area is stabilized with permanent BMPs
  • Initial Close-Out is initiated by the GESC Manager by completing the Initial Close-Out Acceptance Form and attaching the following certifications:  Seeding and Mulching Certification, Topsoil Certification, Initial Close-Out GESC Inspection Certification, Detention / Water Quality Pond Statement, Copy of Probationary Acceptance of Public Improvements Letter (7.1.1-7.1.4).
  • Schedule Initial Close-Out Acceptance Inspection (7.1.5)
  • Upon acceptance of the Initial Close-Out Acceptance Form, Certifications, and Inspection, SEMSWA will grant Initial Close-Out and the Permittee is eligble for the original Collateral Reduction Letter (7.2.5)

5.  Interim Between Initial Close-Out and Final Close-Out

  • Provide GESC Inspections in accordance with the GESC Manual (7.3)
  • NOTE:  THE GESC MANAGER WILL BE REQUIRED TO CERTIFY ALL REQUIRED GESC INSPECTIONS AT BOTH THE INITIAL CLOSE-OUT ACCEPTANCE AND FINAL CLOSE-OUT ACCEPTANCE.

6.  Final Close-Out

  • Once the entire project has reached the required vegetative coverage, in accordance with Section 7.3, the Permittee shall call SEMSWA to schedule a Vegetation Acceptance Inspection (7.4.1)
  • SEMSWA will confirm that the vegetation has met the required coverage and that noxious weeds have been controlled (7.4.2)
  • If the required coverage has been met, SEMSWA will approve the Vegetation Acceptance Form and give the Permittee(s) instruction to remove the remaining onsite BMPs (7.4.2)
  • After approval from SEMSWA, the remaining on-site BMPs shall be removed and the remainder of the site shall be cleaned up and any areas disturbed as a result of the BMP removal shall be seeded and mulched (7.4.3)
  • Final Close-Out is initiated by the GES Manager completing the Final Close-Out Acceptance Form and attaching the following certifications:  Final Close-Out GESC Inspection Certification, Vegetation Acceptance, Copy of Final Acceptance of Public Improvements, Detention / Water Quality Pond Statement (7.4.4)
  • Schedule Final Close-Out Acceptance Inspection (7.4.5)
  • Once Final Close-Out Acceptance has been granted, SEMSWA will approve the Final Close-Out Acceptance form and collateral for the project will be released (7.5)

The Certification Forms for Initial & Final Close-Out Acceptance are contained within this packet.  Please keep these forms until the project is ready for Initial Close-Out Acceptance and/or Final Close-Out Acceptance.


GESC Permit Documents


   Arapahoe County GESC
  • Permit Cover Sheet
  • Permit Instructions
  • GESC Standard Permit
  • Letter of Credit (LOC)
  • GESC Manager Form
  • Initial Close Out Form
  • Initial Close Out Certification
  • Initial Close Out Seeding and Mulching
  • Initial Close Out Topsoil Certification
  • Initial Close Out Pond Volume Certification
  • Final Close Out Form
  • Final Close Out Certification
  • Final Close Out Vegetation Accpetance
  • Final Close Out Pond Volume Certification
  • Low Impact GESC Permit

   City of Centennial GESC
  • Permit Cover Sheet
  • Permit Instructions
  • GESC Standard Permit
  • Letter of Credit (LOC)
  • GESC Manager Form
  • Initial Close Out Acceptance
  • Intial Close Out Certification
  • Final Close Out Acceptance
  • Final Close Out Certification
  • GESC Low Impact Permit